Defects Found at a Chinese Factory: When to Reinspect and Who Pays?
An inspection company reports defective goods at a Chinese factory. The buyer now faces another decision: should the supplier repair the units, replace the shipment, offer a discount, or pay for a second inspection? There is no single answer. A failed inspection is the beginning of a documented corrective-action process, not permission to make assumptions about the entire order.
First establish what failed, where and how
Ask for a precise defect list, test conditions, inspected quantities, photographs, video clips and batch identifiers. Safety failures should not be treated like minor cosmetic marks. If the same faulty component appears across many units, investigating its root cause matters more than merely counting visible defects.
| Finding | Example | Appropriate immediate response |
|---|---|---|
| Critical safety issue | Burned wiring or failed protection | Hold release of affected goods and investigate |
| Functional failure | Item will not start or stops during operation | Repair and demonstrate repeatable functionality |
| Missing content | Incorrect accessory, cable or manual | Recount and complete the affected packages |
| Cosmetic deviation | Scratches or printing errors | Compare with the signed acceptance criteria |
The real MYRON TRADE case: approximately 350 sauna heaters

A client ordered roughly 350 electric sauna heaters from China. The original request was to check 50 units, but four of the first ten tested heaters did not function properly. Some failed to heat, others stopped after operating for a while; temperature-sensor settings caused problems and one heater suffered a wiring failure on startup.
The buyer decided that limited sampling no longer provided enough confidence. MYRON TRADE added two inspectors to the first. Three people worked for about three days, carrying out operational checks and sometimes opening housings. The factory acknowledged the problems and used approximately 10–14 days to correct them. After that, the team checked about 350 heaters again, and the previously identified issues had been resolved.
| Project stage | Documented fact | Why it mattered |
|---|---|---|
| Initial plan | Inspect 50 of approximately 350 units | Defined the original scope |
| Early warning | Four failures in the first ten | Triggered the buyer's decision to expand checks |
| Extended inspection | Three inspectors for roughly three days | Established the condition of the broader batch |
| Factory correction | Approximately 10–14 days | Repairs happened before international transport |
| Repeat inspection | Roughly 350 units checked again | Confirmed corrections rather than relying on a promise |
MYRON TRADE also helped negotiate a discount and compensation for inspection costs from the factory. That outcome belongs to this particular project and is not a guaranteed result for every defect claim.
When is a second factory visit necessary?
An updated photo may be sufficient for a small, clearly localised packaging-label correction if the buyer agrees. It will rarely be sufficient for a heater that overheats, fails during operation or presents an electrical hazard. The retest scope should follow the type of defect, evidence of root-cause correction and the risk that other units share the same problem.
| Corrective action | Evidence to request | Possible reinspection method |
|---|---|---|
| Reprint a limited set of labels | Images tied to batch and carton IDs | Remote check, if acceptable to the buyer |
| Add missing accessories | Updated count and packing photos | Targeted onsite verification |
| Replace faulty electrical components | Working tests under agreed conditions | Onsite functional retest |
| Correct a systematic production defect | Root-cause report and proof of process change | New sampling plan or full checking |
Who pays for the second inspection?

The answer normally depends on the written purchase terms and negotiation. A contract might specify responsibility for defective production and reinspection costs. If it is silent, the buyer may ask the supplier to cover the visit, partly reimburse the cost, issue a discount or agree another remedy. Record the arrangement before the next inspector travels. Claiming that the supplier always pays would be misleading.
An ordinary MYRON TRADE inspection starts in the region of USD 330–350 plus transport, subject to location and scope. Testing hundreds of powered products with several inspectors over multiple days is a different assignment and requires a separate quotation.
A buyer's six-step corrective-action checklist
- Obtain the signed or traceable inspection report, defect images and test notes.
- Match each defect to the specification, accepted sample or purchase contract.
- Ask the factory for a root-cause explanation and dated corrective-action plan.
- Agree whether the next check will be targeted, statistical or 100% of the batch.
- Identify who pays for the second visit and who authorises any payment milestone.
- Release shipment only after the required evidence and commercial approvals are complete.
How MYRON TRADE can help
We can revisit the factory, test repaired units, organise additional inspectors, share images with your team during the visit and support discussions with the Chinese supplier. Where contractual disputes arise, we can involve partner legal professionals. We do not guarantee a refund, supplier compensation or a particular legal result.
Send the previous inspection report, defect list, factory city, quantity and target shipping date. We will propose a realistic retest scope and cost.
Related MYRON TRADE services: quality inspections · legal support.
Send the city, date, project brief and available documents. We will confirm the scope and provide an individual quote.
Need help with this topic?
Describe the task in your own words — even if you are not sure which service you need. A manager will clarify the details and suggest how to proceed and what it will cost.
What happens next
- A manager clarifies the detailsin the channel you choose
- We propose a work plan and a quotewith an estimate of cost and timing
- We agree the terms and startcontract with our company in Shanghai